2016年11月16日星期三

how to install submersible sewage pump ball valve?

Submersible sewage pump The reason why the installation of float valve is because it can be automatically controlled
The principle of the float level controller is as follows: the liquid has buoyancy, while the float system (usually have the appropriate auxiliary equipment) is based on the buoyancy of the liquid and supporting the production, when the liquid level rise, the float system also rose, Similarly, when the liquid level drops, the corresponding drop, when up or down to the set position, the float system will touch the set position of the trip switch (or other microelectronic devices), so that the trip switch to send electrical signals , And electrical control equipment in the received signal will immediately move, cut off or power, the formation of automatic control system.
Submersible sewage pump Float valve installation is relatively complex, it is recommended that the user reference manual for submersible sewage pump to try to install, or sewage pump manufacturers in the past to help install and train personnel how to operate. The following figure in order to illustrate the installation of submersible sewage pump ball valve steps:
Heavy hammer device method:
1, the float switch cable from the center of the heavy hammer into the hole after the hole, gently push the hammer to make embedded in the hole above the plastic ring for the cable head of the thrust and fall off. (If necessary, you can use a screwdriver to remove the plastic ring). And then the shedding of the plastic ring sets in the cable you want to set a fixed weight to set the liquid hammer position.
2, gently push the hammer pull out the cable until the center of heavy hammer buckle plastic ring, heavy hammer as long as the light buckle in the plastic ring that will not fall, the plastic ring if damaged or missing, available with bare copper wire diameter Snap in the cable instead.
Precautions:
1, heavy hammer is required to attach the accessories.
2, please pull the cable directly to the control box, try to avoid the use of intermediate joints. Do not immerse the cable connector in the liquid if it is necessary to do so.
3, unused wires must be absolutely insulated.
If you have any problems during the installation, please call 400-0588-956, Zhengzhou shenlong professional engineers will guide you to one-on-one to complete the installation of submersible sewage pump float valve.